Another step toward a place where life will soon be in full swing. Construction is moving forward every day — and with each new floor, we are getting closer to the moment when bright stories, new families, and warm dreams will begin here.
Here is our latest construction site update:
SECTION 1 – Glazing and façade works completed; ground floor fit-out is underway.
SECTION 2 – Glazing completed on floors 3 and 9–15.
SECTION 3 – Glazing completed on floors 2 and 8–16.
Transformer substation No. 2 has been constructed.
Finalizing monolithic works on the stylobate between Sections 3–7; concreting of vertical structures of the second stylobate level between Sections 2 and 8 completed; foundation works underway for the stylobate between Sections 1 and 9.
SECTION 1 – Concreting of vertical structures of the 14th floor.
SECTION 2 – Finalizing monolithic works.
SECTION 3 – Monolithic works completed; masonry works nearing completion.
SECTION 4 – Finalizing monolithic works; masonry works on floors 2–8.
SECTION 5 – Monolithic works completed.
SECTION 6 – Finalizing monolithic works.
SECTIONS 7–8 – Monolithic works completed; masonry works on floors 2–8.
SECTION 9 – Concreting of vertical structures of the 16th floor.
SECTIONS 1–3 – Concreting of the grillage slab completed.
SECTION 4 – Reinforcement of the basement floor slab.
SECTION 5 – Concreting of the basement floor slab.
SECTION 6 – Reinforcement of the basement floor slab.
SECTION 7 – Reinforcement and concreting of basement vertical structures.
SECTIONS 8–9 – Concreting of the grillage slab completed.
Stylobate façade works in progress; construction of the parking area, commercial spaces, and surrounding landscaping continues.
❗️ To contact our manager, please call:
+38 (044) 334-45-45
❓ Consultations are available at our central office:
19a Metrolohichna Street, Kyiv
Stay safe and support the Armed Forces of Ukraine ❤️ Ukraine will prevail.