Winter is ending at the construction site, and we’re welcoming spring with a new update. Here’s what’s been completed and the current stage of works:
Commissioning stage.
Finalizing the façades, arranging the ground floor, and installing site utilities.
Completed monolithic works on the stylobate between sections 2–8; concreting vertical structures of the above-ground stylobate level between sections 1 and 9.
SECTION 1 – Finalizing monolithic works.
SECTION 2 – Masonry works on floors 3–14.
SECTION 3 – Masonry works completed, window installation has begun.
SECTION 4 – Window installation on floors 14–16.
SECTIONS 5–6 – Monolithic works completed, masonry works beginning.
SECTIONS 7–8 – Masonry works on floors 2–13.
SECTION 9 – Masonry works on floors 2–6.
SECTIONS 1–2 – Reinforcement of basement vertical structures.
SECTION 3 – Completed concreting of the basement floor slab.
SECTION 4 – Reinforcement and concreting of the vertical structures of the 3rd floor.
SECTION 5 – Reinforcement of the 3rd floor slab.
SECTION 6 – Concreting of the 1st floor slab.
SECTION 7 – Concreting of the 1st floor vertical structures.
SECTION 8 – Reinforcement of the 1st floor slab.
SECTION 9 – Concreting of the basement floor slab.
Finalizing the stylobate façades, completing the parking area, commercial premises, and landscaping around the building.
❗️ To contact our manager, please call:
+38 (044) 334-45-45
❓ You can receive a consultation at our central office:
19a Metrolohichna Street, Kyiv
Stay safe and support the Armed Forces of Ukraine ❤️