We are sharing our first construction site update of the new year:
SECTION 1 – Ground floor fit-out works and installation of on-site utilities are underway.
SECTION 2 – Glazing completed; facade painting and ground floor works in progress.
SECTION 3 – Glazing completed on floors 2 and 5–16; finishing facade painting and continuing ground floor works.
Finalizing monolithic works on the stylobate between Sections 2–8; reinforcement and concreting of the basement-level floor slab of the stylobate between Sections 1 and 9.
SECTION 1 – Reinforcement and concreting of the top floor slab and parapet.
SECTION 2 – Monolithic works completed; masonry works underway on floors 4–8.
SECTION 3 – Masonry works completed.
SECTION 4 – Monolithic and masonry works completed.
SECTIONS 5–6 – Monolithic works completed; masonry works starting.
SECTIONS 7–8 – Masonry works on floors 2–10.
SECTION 9 – Monolithic works completed; masonry works underway on floors 2–5.
SECTIONS 1–2 – Reinforcement of basement vertical structures.
SECTION 3 – Concreting of the basement floor slab completed.
SECTION 4 – Reinforcement of first-floor vertical structures.
SECTION 5 – Reinforcement of the first-floor slab.
SECTION 6 – Reinforcement of first-floor vertical structures.
SECTION 7 – Concreting of the basement floor slab completed.
SECTIONS 8–9 – Concreting of basement vertical structures.
Finalizing stylobate facade works; continuing construction of the parking area, commercial premises, and surrounding landscaping.
❗️ To contact our manager, please call:
+38 (044) 334-45-45
❓ You can receive a consultation at our central office:
19a Metrolohichna Street, Kyiv
Stay safe and support the Armed Forces of Ukraine ❤️ Ukraine will prevail