Construction never stops — another month, even more progress. Take a look at how construction is advancing across each building:
Commissioning stage.
Finalizing the façades, arranging the ground floor, and installing site utilities.
Monolithic works on the stylobate are completed; parking entrances are underway.
SECTION 1 – Masonry works on floors 2–12.
SECTION 2 – Window installation on floors 12–16, and wall insulation has begun.
SECTION 3 – Window installation is nearing completion façade insulation and priming in progress.
SECTION 4 – Window installation completed, façade works ongoing.
SECTIONS 5–6 – Masonry works on floors 2–7.
SECTIONS 7–8 – Masonry works completed, window installation on floors 2–9, and wall insulation has begun.
SECTION 9 – Masonry works on floors 2–12.
SECTION 1 – Reinforcement of the vertical structures of the 1st floor.
SECTION 2 – Reinforcement of the 1st floor slab.
SECTION 3 – Reinforcement of the vertical structures of the 1st floor.
SECTION 4 – Reinforcement of the vertical structures of the 10th floor.
SECTION 5 – Concreting of the vertical structures of the 10th floor.
SECTION 6 – Reinforcement of the vertical structures of the 6th floor.
SECTION 7 – Concreting of the vertical structures of the 4th floor.
SECTION 8 – Reinforcement of the vertical structures of the 5th floor.
SECTION 9 – Reinforcement of the 1st floor slab.
Stylobate façades are at the final stage; in parallel, we are arranging the parking, commercial premises, and surrounding landscaping.
❗️ To contact our manager, please call:
+38 (044) 334-45-45
❓ You can receive a consultation at our central office:
19a Metrolohichna Street, Kyiv
Stay safe and support the Armed Forces of Ukraine ❤️