Commissioning stage.
Сompleting the arrangement of the first floor, installing utilities across the site, and carrying out landscaping works.
SECTION 1 – Masonry works is nearing completion, window installation on floors 3-6,8,11.
SECTION 2 – Window installation is nearing completion, façade insulation and priming in progress and have started painting works.
SECTION 3 – Window installation completed, façade works ongoing.
SECTION 4 – Façade works ongoing and have started painting works.
SECTIONS 5–6 – Masonry works is nearing completion and have started window installation.
SECTIONS 7–8 – Window installation on floors 2–13, façade insulation and priming in progress and have started painting works.
SECTION 9 – Masonry works on floors 2–12.
SECTION 1 – Concreting of the 1st floor slab.
SECTION 2 – Reinforcement of the 2nd floor slab.
SECTION 3 – Reinforcement of the 1st floor slab.
SECTION 4 – Reinforcement of the vertical structures of the 12th floor.
SECTION 5 – Concreting of the vertical structures of the 12th floor.
SECTION 6 – Reinforcement of the 7th floor slab.
SECTION 7 – Reinforcement of the vertical structures of the 6th floor.
SECTION 8 – Reinforcement of the vertical structures of the 6th floor.
SECTION 9 – Reinforcement of the vertical structures of the 3rd floor.
Installing site utilities and carrying out works on the parking area, commercial spaces, and site landscaping.
❗️ To contact our manager, please call:
+38 (044) 334-45-45
❓ You can receive a consultation at our central office:
19a Metrolohichna Street, Kyiv
Stay safe and support the Armed Forces of Ukraine ❤️