Commissioning stage.
Finishing the commercial area, installing site utilities, laying pavers, and proceeding with landscaping.
SECTION 1 – Masonry completed; glazing installed on floors 3–12.
SECTION 2 – Glazing completed; façade priming and painting in progress.
SECTION 3 – Façade insulation and painting nearing completion; installation of AC unit brackets has begun.
SECTION 4 – Façade works and painting ongoing.
SECTION 5 – Masonry completed; glazing installed on floors 2–14.
SECTION 6 – Masonry nearing completion; glazing installed on the 3rd floor.
SECTIONS 7–8 – Glazing nearing completion; wall insulation and façade painting ongoing.
SECTION 9 – Masonry completed; glazing installed on floors 3–4 and 6–7.
SECTION 1 – Concreting of the 1st floor slab.
SECTION 2 – Rebar reinforcement for the 4th-floor vertical elements.
SECTION 3 – Rebar reinforcement for the 2nd-floor vertical elements.
SECTION 4 – Concrete pouring for the 12th-floor vertical elements; masonry has begun.
SECTION 5 – Rebar reinforcement for the 12th-floor slab.
SECTION 6 – Concrete pouring for the 9th-floor slab.
SECTION 7 – Concrete pouring for the 8th-floor vertical elements.
SECTION 8 – Concrete pouring for the 7th-floor vertical elements.
SECTION 9 – Rebar reinforcement for the 4th-floor slab.
Constructing the access road, installing utilities, preparing the parking area and commercial spaces, and focusing on landscaping for your future home — we have already installed the first children’s playgrounds and sports equipment.
❗️ To contact our manager, please call:
+38 (044) 334-45-45
❓ You can receive a consultation at our central office:
19a Metrolohichna Street, Kyiv
Stay safe and support the Armed Forces of Ukraine ❤️